ACQUIRING FIRE CERTIFICATE/PERMIT

STEP 1:  Request for inspection and submit following to the Fire Department each of them with dimensions

  1. Site Plan
  2. Block Plan
  3. Floor Plan

STEP 2:  Inspection of Project/Building by Fire Department.

STEP 3:  Present Fire Engineering drawings to the Fire Department.

STEP 4:  Apply for Fire Certificate/Permit from the Fire Department.

STEP 5:  The Fire Department operates a Risk based system. Categorized as:

  1. Low Risk Projects
  2. Medium Risk Projects
  3. High Risk Projects

STEP 6:  The turnaround time for the majority of projects (Low Risk) is five (5) days.

Issued by Fire Safety Directorate.