Steps to Acquire a Fire Certificate/Permit
- Request for inspection and submit the following to the Fire Department (each with dimensions):
- Site Plan
- Block Plan
- Floor Plan
- Inspection of Project/Building by Fire Department.
- Present Fire Engineering drawings to the Fire Department.
- Apply for Fire Certificate/Permit from the Fire Department.
- The Fire Department operates a Risk-based system. Projects are categorized as:
- Low Risk Projects
- Medium Risk Projects
- High Risk Projects
- Turnaround time for most projects (Low Risk) is five (5) days. Issued by Fire Safety Directorate.
For more information or assistance, please contact the Fire Safety Directorate.