Acquiring Fire Certificate/Permit

ACQUIRING FIRE CERTIFICATE/PERMIT

STEP 1:

Request for inspection and submit following to the Fire Department each of them with dimensions.
1. Site Plan
2. Block Plan
3. Floor Plan

STEP 2.

Inspection of Project/Building by Fire Department.

STEP 3.

Present Fire Engineering drawings to the Fire Department.

STEP 4.

Apply for Fire Certificate/Permit from the Fire Department.

STEP 5.

The Fire Department operates a Risk based system. Categorized as:
1. Low Risk Projects
2. Medium Risk Projects
3. High Risk Projects

STEP 6.

The turnaround time for the majority of projects (Low Risk) is five (5) days.
Issued by Fire Safety Directorate.